HVDC Troll
60°40′00″N 3°40′00″E / 60.66667°N 3.66667°E / 60.66667; 3.66667 (Kollsnes-Troll Transmission - Troll A Static Inverter Plant (situated on Troll A offshore platform))
184 MW (after 2015)
56 kV (Troll)
The HVDC Troll is a bipolar high-voltage direct current (HVDC) electric power transmission line for the supply of the gas compressor station on the offshore construction work Troll A platform. It consists of dual set of a 68-kilometre (42 mi) long bipolar submarine cable designed for ±60 kV between the inverter at the Troll A platform and the static rectifier station at Kollsnes in Norway. The HVDC Troll has a maximum transmission rate of 84 megawatt.
In 2013 work started on a new rectifier station at Kollsnes for supplying the two new compressors being installed on Troll A.
Sites
Site | Coordinates |
---|---|
Kollsnes Static Inverter Plant | 60°33′01″N 4°50′26″E / 60.55028°N 4.84056°E / 60.55028; 4.84056 (Kollsnes-Troll Transmission - Kollsnes Static Inverter Plant) |
Offshore platform Troll A | 60°40′00″N 3°40′00″E / 60.66667°N 3.66667°E / 60.66667; 3.66667 (Kollsnes-Troll Transmission - Troll A Static Inverter Plant (situated on Troll A offshore platform)) |
See also
References
Working Group on HVDC and FACTS Bibliography and Records (2008-07-07). "HVDC PROJECTS LISTING" (PDF). IEEE Transmission and Distribution Committee. Archived from the original (PDF) on 2008-12-15. Retrieved 2008-12-19.
External links
Download coordinates as:
- KML
- GPX (all coordinates)
- GPX (primary coordinates)
- GPX (secondary coordinates)
- Troll HVDC Light transmission, Norway, The ABB Group.
- v
- t
- e
This article about a Norwegian building or structure is a stub. You can help Wikipedia by expanding it. |
- v
- t
- e